Contract signing date
Neither date is silently preferred. Seek a primary clarification.
Edits here will not overwrite it. New edits are kept in a separate local recovery copy when browser storage is available. Export this draft, or reload the saved version and use “Recover unsaved edits” in My brief.
Public procurement · Preserve the contradiction
2025 procurement · signing dates conflict
WHAT THE HELD EVIDENCE SAYS
Retain both dates and their sources. Supplier testimony on manufacturing and enterprise size needs independent corroboration.
Contract cover says 23 August 2025; portal says signed 5 September 2025. Date conflict retained. Acceptance and payment remain open.
01 · IMPLEMENTATION
Recorded stages describe the review snapshot. An open stage means it is not established here; it is not a finding of failure.
STRESS-TEST THE CONCLUSION
Reasoning checks grounded in the reviewed case. Open a claim to see what supports it, what it would overstate and the next test.
The portal reports 5 September, while the stamped contract cover reads 23 August. Both assertions are retained.
Neither source is silently treated as the corrected date.
Next test: Seek an authority clarification or a documented explanation of the date fields.
Editorial reasoning aid based on the 2026-10-24 review snapshot; not a new independent adjudication.
The published declaration states micro-enterprise status and identifies the supplier as manufacturer. It is bidder testimony.
Visual transcription confirms the reviewed wording, not independent enterprise-size or ownership verification.
Next test: Check the relevant entity and period using independent corroborating records.
Editorial reasoning aid based on the 2026-10-24 review snapshot; not a new independent adjudication.
02 · COMPETING RECORDS
Neither date is silently preferred. Seek a primary clarification.
Retain the distinct field meanings; this does not establish missing delivery.
CLAIM → CLAUSE → ORIGINAL
Text matching checks the saved wording. It does not establish that a claim is true or that an event occurred.
91320585MA1P3T883LAward and contract consideration, not a grant or payment. Contract-summary quantity 1 differs from the award quantity 2; retain both source meanings.
Not established; original review snapshot and automated text check are distinct.
Receipt receipt-f18872fe636d2e9c
Source SHA-256 4dde416f117ecab1d7f91d3fec745c146765021cda8a405b0d9fe6c224b2a9c1
Review SHA-256 4dde416f117ecab1d7f91d3fec745c146765021cda8a405b0d9fe6c224b2a9c1
制造商为苏州鄂尔精密机械有限公司 … 属于微型企业Bidder declaration checked visually; not independent verification of enterprise size or ownership.
Not established; original review snapshot and automated text check are distinct.
Receipt receipt-cb013ac3dce4420e
Source SHA-256 ca82c2f98bf16b40bdada2ad49e25db9f8a157d32f168454ee876d45d91a789d
Review SHA-256 ca82c2f98bf16b40bdada2ad49e25db9f8a157d32f168454ee876d45d91a789d
DOCUMENT CHRONOLOGY
Procurement call (third notice), published on composite portal page
Source S105 ↗Supplier SME / manufacturer declaration
Source S130 ↗Award announced: two lathes, RMB1,090,000
Source S105 ↗Stamped contract cover signing date — conflicts with portal
Source S121 ↗Portal-reported signing date — conflicts with original cover
Source S105 ↗Contract notice published
Source S105 ↗PRESERVED EVIDENCE
Availability is checked locally. Each original download verifies its bytes against the stored SHA-256. Matching source metadata is a separate check.
contract · extracted
Published URL: https://czju.suzhou.gov.cn/zfcg/html/project/d67f0dadd031453985832a8d03cbc05b.shtml
Retrieved: 2026-10-24T09:09:15.528600+00:00
Snapshot version: matches_snapshot
4dde416f117ecab1d7f91d3fec745c146765021cda8a405b0d9fe6c224b2a9c1annex · extracted
Published URL: https://czju.suzhou.gov.cn/zfcg/informations/rules/downFile.action?filePath=1ca8731c623c43549069817cf8cc6e95
Retrieved: 2026-10-24T09:11:59.199949+00:00
Snapshot version: matches_snapshot
f5100573e2d488e4dfe6d10f3eb5d21d26c3bc42a6051806611fdc6d82210b1eannex · extracted
Published URL: https://czju.suzhou.gov.cn/zfcg/informations/rules/downFile.action?filePath=f2512f156fce485c962c689e579b9903
Retrieved: 2026-10-24T09:12:02.431886+00:00
Snapshot version: matches_snapshot
ca82c2f98bf16b40bdada2ad49e25db9f8a157d32f168454ee876d45d91a789dannex · extracted
Published URL: https://czju.suzhou.gov.cn/zfcg/informations/rules/downFile.action?filePath=ddbabec94bef4669b5486d9377cd57ff
Retrieved: 2026-10-24T09:12:05.186789+00:00
Snapshot version: matches_snapshot
f51f2ec05c49b84dda5430545ab16389fdacef25ff2cd4e5cffb4e50c94c16eaLoading current evidence…